Completed the installation of a contact insulation
In recent months, we’ve completed the installation of a contact insulation system in two sections, and we’re currently installing the roof cladding in section B.
May 2025
The rough construction is complete!
March 2025
Formwork and reinforcement for 3. floor, section C
We’ve installed formwork and reinforcement for the ceiling slab of the third floor of section C.
August 2024
The ceiling slab of the basement is in place
The ceiling slab of the basement is in place, and the concrete work on the first floor of section C is also complete. Geotextile protects the structure from direct sunlight to prevent the concrete from overheating.
July 2024
We’ve installed formwork
We’ve installed formwork for concreting the ceiling slab on the first basement level.
June 2024
We’ve laid the "white tub"
We’ve laid the reinforcement for the “white tub,” which we’ll then fill with special impermeable concrete. This solution replaces waterproofing.
April 2024
We’ve completed and secured the construction pit
We’ve completed and secured the construction pit. The foundation joint for laying the base concrete has also been prepared and stabilized.